20/3 | Project plan ready | OK |
21/3 | System modelled | OK |
28/3 | Balancing controller designed | OK |
28/3 | Progress report 1 | OK |
2/4 | Swinging controller designed | OK |
4/4 | Progress report 2 | OK |
8/4 | Total controller designed | OK |
8/4 | Balancing controller in DSP | OK |
10/4 | Midterm review | OK |
11/4 | Swinging controller in DSP | OK |
11/4 | Progress report 3 | OK |
6/5 | Controller with safety features | OK |
6/5 | Swing and balance controllers in DSP | OK |
9/5 | Progress report 4 | OK |
14/5 | Final controller design | OK |
16/5 | Final controller in DSP | OK |
16/5 | Progress report 5 | OK |
20/5 | Final review | OK |
23/5 | Final written report | OK |