Week 7: 04-28 to 05-04

 

Pendubot

Progress report 6

 

 

1.        Recall of the objectives:

 

*     Update the website

 

*     Create the application file

 

*     Finish the first version of the final report

 

*     Write the user manual

 

*     Work on the poster

 

2. Achieved work:

 

*     Update the website

*     Add the last reports

*     Add some simulations

 

*     Create the application file

*     We still have problem with the creation

 

*     Finish the first version of the final report

 

*     Write the user manual

 

*     Work on the poster

*     Almost finished, we just have to add a team’s picture

 

1. Problems:

 

Problem with the creation of the application file

 

2. Objectives of next week:

 

 

*     Manage to create our application file

*     Prepare the final presentation

*     Update the website

*     Correct the final report, the user manual

 

 

 

 

Global progress of the project (Schedule’s update)