Week 6: 04-21 to 04-27

 

Pendubot

Progress report 5

 

 

 

1.        Recall of the objectives:

 

*     Update the website

 

*     Finish the program

 

*     Write the final report

 

2. Achieved work:

 

 

*     Update the website

*     Problem of display with Mozilla solve

*     New design for the Webpages

 

*     Finish the program

*     problem of last week solved

*     design of the interface finished

 

*     Write the final report

 

*     Poster

*     almost finished

 

 

 

3. Problems:

 

Problems when the motor warms up, but we’ve fixed it.

 

 

4. Objectives of next week:

 

*     Finish the first version of the final report

*     Finish the first version of the poster

*     Finish the first version of the user manual

*     Create the execution file

 

 

 

Global progress of the project (Schedule’s update)